CLOSE SEARCH
With many construction projects, sub-contracting is a necessary and important part of the project.
Where a sub-contractor is engaged, the main contractor is still ultimately responsible for fulfilling all the obligations under the construction contract with its employer, even if it is one of the sub-contract team who fails to perform.
Our team of specialist lawyers draft, negotiate and finalise sub-contracting arrangements and advise on issues arising on sub-contracts, including disputes. We advise employers, main contractors and also sub-contractor clients.
Our experience and sector focus results in clear, practical, cost-effective advice on the most important issues.
The employer should review sub-contracting arrangements to ensure they support and align with the main contract. By way of example, the employer will want to ensure that the sub-contracting costings align, and relevant performance requirements match those in the main contract.
Some key areas to consider include :-
Due diligence on and/or ability to veto sub-contractors - verify the financial health of potential sub-contractors to assess their ability to complete their work, evaluate their track record, references, and experience in similar projects, and ensure they have adequate insurance coverage.
Incorporating main contract terms - relevant terms from the main contract should be cited or incorporated into the sub-contract to avoid ambiguities, gaps, or movement away from a ‘back-to-back’ arrangement.
Sub-contracting assignment and novation - the employer should have control over sub-contractor changes.
Liquidated damages - ensure the main contractor has properly ‘stepped-down’ liquidated damages arrangements, so it can recover sufficient funds to meet its liabilities under the main contract.
Collateral warranties
From the main contractor's perspective, it will be important to avoid a poor ‘pass-down’ of key commercial obligations, gaps in liability, and/or otherwise failing to ensure there is a sensible ‘back-to-back’ arrangement with the main contract.
The main contractor will want to ensure there are no gaps between its obligations under the main contract and the sub-contractor's obligations under the sub-contract. If there are any problems the risk is likely to sit with the main contractor.
A key concern for the main contractor will be ensuring there is sufficient 'headroom' under the sub-contract to be able to perform its obligations in the main contract. For example, if the contractor is obliged to notify the employer under its main contract of a Relevant Event within 14 days, when ‘stepping-down’ that same obligation into the sub-contract, the main contractor will want to impose a shorter period on the sub-contractor to exercise that same right. In that context, issues which we typically emphasise can include :-
Payment – to avoid the need to pay sub-contractors before receipt of relevant sums from its employer, a contractor should seek to set up its contractual arrangement so that there is a suitable ‘buffer period’ between payments. Any such mechanism will need to be mindful of laws prohibiting conditional payment / ‘pay-when-paid’ clauses.
Dispute resolution - the contractor will want to ensure there is coordination between the dispute resolution procedures in the main contract and sub-contract.
Liability caps - review liability caps in both contracts and assess potential risks. If caps are more limited in the sub-contract than in the main contract, the main contractor will be taking on that risk.
We also regularly advise sub-contractors on the inherent risks which may include :-
Sub-contractor’s obligations
Payment terms .
Time - the sub-contractor should seek a mechanism which allows applying for more time, resulting in an extension to the date for completion of the sub-contract works, thereby avoiding any liquidated damages for late delivery.
Dispute resolution - a suitable mechanism to resolve disputes which may arise between the parties, including processes such as negotiation, mediation, and/or adjudication.
Termination rights - the grounds for the termination of the sub-contract and the consequences which will follow, including payment on termination.
Insurance - the types and levels of insurance required.
Telephone -
9am to 5pm
Solicitor - Construction & Engineering
Daniel is a specialist construction lawyer with 14 years post qualified experience of advising a broad range of clients on contentious and non-contentious issues.
Other experts who have experience in this area.
Call the Taylor Rose team or fill out the form below and we will get back to you as soon as possible.
Telephone opening hours -
9am to 5pm